Work Packages
WP1
Management and Coordination
Start: Month 1 – End: Month 36
April 2024 – March 2027
Establishing smooth, effective management and coordination procedures to ensure on-time, on-budget project implementation and strong communication among partners #ProjectManagement #EffectiveCoordination
WP2
Preparation
Start: Month 1 – End: Month 6
April 2024 – September 2024
Leading the project by refining its approach and focus through targeted surveys, best practices, and strategic planning. Outcomes will shape the next phases and lay the foundation for key project outputs #ProjectLeadership #StrategicPlanning
WP3
Development I: LAB Network
Start: Month 7 – End: Month 18
October 2024 – September 2025
Establishing lab units with strong internal and external integration by building essential hard capacities, including equipment, software, and organizational structure. Supported by benchmarking visits for effective, sustainable operation #CapacityBuilding
WP4
Development II: Modernizing Curricula
Start: Month 7 – End: Month 18
October 2024 – September 2025
Modernizing curricula at SEMED HEIs to address urban sustainability, integrating emerging tech, best practices, and interdisciplinary knowledge, in collaboration with EU partners and stakeholders #CurriculumModernization #SustainableEducation
WP5
Development III: Training
Start: Month 7 – End: Month 18
October 2024 – September 2025
Enhancing competences of HEI staff to deliver new curricula and lab units effectively, ensuring long-term sustainability through targeted training based on capacity surveys #SkillsDevelopment #SustainableEducation
WP6
Synergized Lab-Curriculum Delivery
Start: Month 19 – End: Month 36
October 2025 – March 2027
Delivering the master’s program at UOP, modules at partner HEIs, and fully functioning lab units, using modernized curricula and joint labs. Includes testing innovative measures and ongoing evaluation to ensure sustainability #ProjectDelivery
WP7
Quality Assurance. Monitoring. Evaluation
Start: Month 1 – End: Month 36
April 2024 – March 2027
Establishing quality control, monitoring, and evaluation processes to ensure high-quality outputs, consistency, and timely delivery of project milestones #QualityAssurance #ProjectMonitoring
WP8
Dissemination. Exploitation. Sustainability
Start: Month 1 – End: Month 36
April 2024 – March 2027
Developing and executing a comprehensive communication plan to promote the project, engage targeted audiences, and maximize impact. Includes detailed strategies for internal and external dissemination, #ImpactMaximization
Progress
- WP1: Management and Coordination 30%
- WP2: Preparation 100%
- WP3: Development I: LAB Network 10%
- WP4: Development II: Modernizing Curricula 0%
- WP5: Development III: Training 0%
- WP6: Synergized Lab-Curriculum Delivery 0%
- WP7: Quality Assurance. Monitoring. Evaluation 30%
- WP8: Dissemination. Exploitation. Sustainability 50%